Sawaed Real Estate Al Hamra 105 Project

36%Overall▲ +8% · vs previous visit

Main video

Engineering Report

The project has shown significant progress in the structural framework and masonry work, with the completion of several additional floors and the commencement of utility installations and initial finishing works.
Detected changes
Concrete Structure100%

Completion of casting columns and slabs for typical floors up to the formwork stage of the final roof, with vertical installations visible.

Masonry Works95%

Execution of wall construction using red and cement blocks on the lower and middle floors, including the partitioning of interior spaces.

Plumbing and Electrical Works85%

Commencement of vertical drainage pipe installation and the rough-in of electrical conduits within the constructed walls.

General Site90%

Organization of the work area surrounding the building, with ongoing storage of construction materials (blocks and timber).

Progress reading

The images align with the observed increase in concrete works (+20%), as progress moved from pouring the initial slabs to a nearly complete structure; the start of initial finishing and masonry works is also clearly visible at a rate of 10%.

vs previous visit

Compared to the previous visit, which only showed the casting of the ground/first-floor ceiling, the current images show the vertical structure rising across several floors and the commencement of the masonry phase, which was entirely absent during the previous visit.

Expected next milestones

Completion of the final roof slab casting, commencement of internal plastering works, and intensification of plumbing and electrical installations.

Progress

0%OverallAverage item progress
1/5 completeavg ▲ +8%
Excavation Works
0%
Concrete Works▲ +20%
0%
Finishing Works▲ +10%
0%
Electrical Works▲ +5%
0%
Plumbing Works▲ +5%
0%