Sawaed Real Estate Al Hamra 105 Project
Main video
Engineering Report
Detected changes
Completion of casting columns and slabs for typical floors up to the formwork stage of the final roof, with vertical installations visible.
Execution of wall construction using red and cement blocks on the lower and middle floors, including the partitioning of interior spaces.
Commencement of vertical drainage pipe installation and the rough-in of electrical conduits within the constructed walls.
Organization of the work area surrounding the building, with ongoing storage of construction materials (blocks and timber).
Progress reading
The images align with the observed increase in concrete works (+20%), as progress moved from pouring the initial slabs to a nearly complete structure; the start of initial finishing and masonry works is also clearly visible at a rate of 10%.
vs previous visit
Compared to the previous visit, which only showed the casting of the ground/first-floor ceiling, the current images show the vertical structure rising across several floors and the commencement of the masonry phase, which was entirely absent during the previous visit.
Expected next milestones
Completion of the final roof slab casting, commencement of internal plastering works, and intensification of plumbing and electrical installations.